That's a 2014-2015 link?
They aren't operational yet.
https://www.spglobal.com/platts/en/m...-plant-to-2020
Quote:
Commercial operation of the 1.1-GW plant, the only coal-fired power station in construction in Western Europe, was due to commence in Q4 2019, but initial testing of the plant in 2017 resulted in damage to the boiler in conjunction with the use of T24 steel.
The damage has since been under review, Uniper said, and initial findings "indicate that the boiler walls will have to be replaced to remedy the damage."
"This will delay the plant's planned commissioning, which will now presumably take place in the summer of 2020"
|